Air Conditioning Mechanical Ventilation (ACMV), Project Managements

Hospital Umum Kuching, Sarawak

Cadangan Penggantian Sistem Penyaman Udara Berpusat Termasuk AHU Dan Peralatan-Peralatan Lain Berkaitan Untuk Bangunan Pesakit Luar Hospital Umum Sarawak

 

Scope & System Under Supervision

1. Decommissioning & Demolition

  • Careful dismantling and removal of existing obsolete chillers, cooling towers, and water pumps.
  • Removal of existing Air Handling Units (AHUs) and Fan Coil Units (FCUs) without disrupting hospital operations.
  • Safe disposal of all decommissioned mechanical components in accordance with environmental guidelines.

2. Chiller Plant System Installation

  • Supply, delivery, and installation of new Water-Cooled Chillers designed for high energy efficiency.
  • Installation of specialized Chilled Water Pumps and Condenser Water Pumps.
  • Supply and installation of high-performance Cooling Towers.

3. Air-Side & Piping Upgrades

  • Installation of new Air Handling Units (AHU) and Fan Coil Units (FCU).
  • Retrofitting and installation of chilled water piping, including premium insulation to prevent thermal loss.
  • Re-configuration of ductwork and air distribution systems to optimize airflow in outpatient areas.

4. Electrical & Control Systems

  • Supply and installation of Motor Control Centers (MCC) and Starter Panels.
  • Integration of a Building Management System (BMS) for real-time energy monitoring and automated HVAC control.
  • Installation of Variable Speed Drives (VSD) to enhance energy savings for motors and fans.

5. Testing & Commissioning  (T&C)

  • Comprehensive pressure testing of the piping network.
  • Performance validation of the chiller plant to ensure it meets the required Cooling Tonnage and efficiency ratings.
  • Handover of “As-Built” drawings and Operation & Maintenance Manuals (OMM).